INSTALLATION
1.
Install primary air gauge (Figure 2, Item 5) on instrument cluster (Figure 2, Item 6).
2.
Install gauge mounting bracket (Figure 2, Item 4) on primary air gauge (Figure 2, Item 5) with two lockwashers
(Figure 2, Item 3) and nuts (Figure 2, Item 2).
NOTE
Male pipe threads must be wrapped with antiseize tape before installation.
3.
Connect air line (Figure 2, Item 1) to primary air gauge (Figure 2, Item 5).
4.
Install instrument cluster (Figure 2, Item 6) on instrument panel (Figure 2, Item 8) with eight screws
(Figure
2,
Item
7).
M0198DAA
1
2
3
4
8
6
7
5
Figure 2.
Air Gauge Installation.
END OF TASK