Table 1. Preventive Maintenance Checks and Services (PMCS) - Continued.
ITEM
NO.
INTERVAL
ITEM TO BE
CHECKED OR
SERVICED
PROCEDURE
EQUIPMENT NOT
READY/AVAILABLE
IF:
INTERIOR
NOTE
The Air Conditioning
Kit is installed on
vehicles equipped with
Crew Protection Kit
only.
If vehicle is equipped
with air conditioning,
perform during operation
step 22.
22
During
A/C Blower
Unit
a. Start engine, refer to
WP 0008 or WP 0009.
b. Turn A/C switch
(Figure 15, Item 1)
ON and fan speed
switch
(Figure 15, Item 3) to
HIGH position
(WP 0005).
c. Operate A/C system
for five minutes and
check temperature of
air coming out of
blower unit vents
(Figure 15, Item 2).
Temperature of
air coming out
of vents is not
cold and A/C is
required for
mission.
1
2
3
Figure 15. A/C Blower Unit.