TM 9-2320-328-13&P-1
0022-5/(6 blank)
DRAFT
0022
Change 1
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
14. Turn foam manual METERING VALVE (7) to OPEN position.
15. Water must be added into foam tank (5) that is being flushed.
16. Run foam system with water instead of foam (WP 0024).
17. Discharge water until foam tank (5) is empty.
18. All debris must be removed from foam tank (5) after flushing is complete.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
19. Install fill tower screen (6) in foam tank (5).
20. Close expansion dome hatch (3).
21. Flush foam system (WP 0029).
END OF TASK
END OF WORK PACKAGE
HWT0499
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
HWT0496