TM-9-2320-328-13-P-1

HEMTT-BASED WATER TENDER (HEWATT)

TECHNICAL MANUAL; OPERATOR’S AND FIELD LEVEL MAINTENANCE MANUAL (INCLUDING REPAIR PARTS AND SPECIAL TOOLS LIST); PART 1 OF 3

MARCH 2009

  TM-9-2320-328-13-P-1 - Page 440 of 1318

TM 9-2320-328-13&P-1
0060-4
DRAFT
0060
END OF TASK
FOLLOW-ON MAINTENANCE
Remove wheel chocks (TM 9-2320-422-10)
END OF TASK
END OF WORK PACKAGE
HWT0325A
Step 4.
Push NO. 1 DRIVER SIDE DISCHARGE valve control FLOW button (WP 0004). Check
position of manual metering control valve. Ensure that manual metering valve is set to
match output of NO. 1 DRIVER SIDE DISCHARGE valve control (WP 0021).
Set
manual metering control valve to proper adjustment using manual metering control
valve data plate valve settings.
Start engine (TM 9-2320-422-10).
Set up system to
pump from tank (WP 0019).
Turn on foam system (WP 0024).
Check if foam is
delivered when system is operated.
Turn off foam system (WP 0024).
Flush foam
system (WP 0022).
a.
If foam is delivered, problem has been corrected.
Notify Supervisor.
b.
If foam is not delivered, replace manual metering valve (WP 0181).
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION


Back to Top