TM 9-2320-328-13&P-3
0340-26
DRAFT
0340
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
NOTE
•
Both electrical valve control meters are installed the same way.
Passenger side discharge
electric valve control meter shown.
•
Install cable ties as required.
37. Connect flow sensor wire harness connector (6) on electric valve control meter flow sensor connector (5).
38. Connect pressure transducer wire harness connector (4) on electric valve control meter pressure transducer
connector (3).
39. Connect valve control wire harness connector (2) on electric valve control meter motor connector (1).
40. Repeat Steps (37) through (39) for driver side discharge electric valve control meter.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Close pump operator’s panel (WP 0207)
2.
Install battery box (WP 0238)
3.
Install pump house panels L, K, H, G, E, B, and A (WP 0339)
4.
Install power take off (PTO) drive shaft (WP 0154)
5.
Fill hydraulic reservoir (WP 0145)
END OF TASK
END OF WORK PACKAGE
HWT2968