NOTE
The slings and hardware required for this operation are found in the
19. Attach large ring of bridge bay sling (28) to hook of snatch block (26).
20. Turn HIGH IDLE switch (19) to ON position.
21. If this is an interior bay, attach intermediate cable hooks on two sling legs to large ring
of sling.
22. Position HOOK ARM switch (20) to LOAD and release when hook arm is fully retracted.
23. Position remote WINCH switch (21) to IN and release when top of snatch block (26) is
about 9 in. (23 cm) from bottom of extension assembly (25).
24. Position MAIN FRAME switch (22) to load and release when snatch block (26) is about
9 ft. (2.8 m) above ground.
25. Set remote HIGH IDLE switch (19) to OFF position.
CAUTION
Damage to equipment may occur if vehicle is backed up and the BAP
makes contact with bridge bay.
26. Push in PARKING BRAKE control (7).
Alison
Transmision
8X8
TRAILER
AIR SUPLY
PUSHT
M
M
7
8
Figure 10.
TM 9-2320-346-10
0104
0104-13