FOLLOW-ON TASKS: • Install A/C front air distribution duct (para. 11-81).
• Connect battery ground cables (para. 4-68).
10-67. WINDSHIELD DE-ICER, DEFROSTER SWITCH, AND CIRCUIT BREAKER
REPLACEMENT
(Cont’d)
TM 9-2320-387-24-2
Change 1
10-115
10.
Connect lead (28) to body harness connector (27).
11.
Connect lead (5) to rotary switch (2).
12.
Apply sealing compound (1) and (10) to end of instrument panel (3) and to ends of cables (4), (9),
and (11).