TM-9-2320-440-13-P

TERMINAL HIGH ALTITUDE AREA DEFENSE (THAAD) CARRIER

TECHNICAL MANUAL; OPERATOR’S AND FIELD LEVEL MAINTENANCE MANUAL (INCLUDING REPAIR PARTS AND SPECIAL TOOLS LIST)

AUGUST 2010

  TM-9-2320-440-13-P - Page 704 of 1616

TM 9-2320-440-13&P
0090-2
0090
INSTALLATION
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
NOTE
Both outrigger and MRP work lamp switches are installed the same way.
Outrigger work
lamp switch shown.
Install cable ties as required.
1.
Install switch (7) and switch bracket (6) on bracket (8) with two screws (5), washers (4) and locknuts (3).
2.
Connect connector (2) to connector (1).
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Connect batteries (TM 9-2320-325-14&P).
2.
Remove wheel chocks (
END OF TASK
END OF WORK PACKAGE
THAAD0151
TM 9-2320-347-10)


Back to Top