INSTALLATION - Continued
24.
Install air reservoir (Figure 8, Item 4) on brackets (Figure 8, Item 2) with two U-bolts (Figure 8, Item 3) and four
locknuts (Figure 8, Item 1).
1
2
3
4
1
Figure 8.
Air Reservoir No. 1 Installation.
25.
Install air lines 2615 (Figure 9, Item 1) and 2229 (Figure 9, Item 2) on fittings (Figure 9, Item 4) and (Figure 9,
Item 3).
1
2
3
4
Figure 9.
Air Reservoir No. 1 Installation.
26.
Install air lines 2228 (Figure 10, Item 4), 2248 (Figure 10, Item 6), and 2224 (Figure 10, Item 1) on fittings
(Figure 10, Item 3), (Figure 10, Item 5), and (Figure 10, Item 2).
TM 9-2330-342-23&P
0068
0068-7