21.
Apply sealing compound to threads of rear No. 2 air tank fitting (Figure 11, Item 6).
22.
Install air harness connector 2019 (Figure 11, Item 8) on rear of No. 2 air tank fitting (Figure 11, Item 6).
23.
Apply sealing compound to threads of right side of No. 2 air tank fitting (Figure 11, Item 5).
24.
Install air harness connector 2606 (Figure 11, Item 7) on right side of No. 2 air tank fitting (Figure 11, Item 5).
25.
Install air harness connector 2078 (Figure 11, Item 3) on rear right of the right load lock air chamber fitting
(Figure 11, Item 4).
26.
Apply sealing compound to threads of top right No. 2 relay valve fitting (Figure 12, Item 4).
10
11
10
1
2
3
4
5
6
7
8
9
Figure 12.
Trailer Air Harness Installation.
27.
Install air harness connector 2638 (Figure 12, Item 5) on top right of No. 2 relay valve fitting (Figure 12, Item