TM 9-2350-261-20-3
REPLACE STOWAGE BRACKETS FOR W1, W2, AND NATO
SLAVE CABLES (M1068 ONLY)
0545 00
THIS WORK PACKAGE COVERS:
Removal (page 0545 00-1).
Installation (page 0545 00-2).
INITIAL SETUP:
Maintenance Level
Unit
Tools and Special Tools
General Mechanic’s Tool Kit (WP 0780 00, Item 29)
Materials/Parts
Lockwasher (3)
Personnel Required
Unit Mechanic
Equipment Condition
Engine stopped (see your -10)
Carrier blocked (see your -10)
All cables removed from brackets (see your -10)
REMOVAL
NOTE
There are two stowage brackets per location. Two stowage brackets secure the stowed NATO
slave cables and the other two stowage brackets secure the stowed W1 and W2 power
distribution cables. They are all removed and installed the same way. Only one is shown.
054500-1
1.
Remove three screws (3), washers (1), lockwashers (2), and bracket (4) from carrier. Discard lockwashers.