0269 00
INSTALLATION
1.
Install distribution box (8) on hull. Secure with five screws (12) and new lockwashers (13).
2.
Install circuit leads 450 (9), 450B (10), and two new grommets (11) in distribution box (8).
3.
Install circuit leads 6 (3), 6A (4), 6L (5), 49 (6), and four new grommets (7) in distribution box (8). Secure leads to bus
bar (14) with two screws (1) and new lockwashers (2).
4.
Install new grommet (15) on circuit lead 2 (16) and new grommet (17) on circuit lead 2A (18). Route leads into
distribution box (8), and install grommets in box.
NOTE
Step 5 applies to M113A3 carriers with water/ration heater kit installed only.
5.
Install circuit lead 222B (25) and grommet (26) in distribution box (8).
6.
Install lead 400 (19) in distribution box (8).
0269 00-4
REPLACE DISTRIBUTION BOX (M113A3,M1059A3, M1064A3, AND M58 ONLY)