c. Harness Connections.
(1) 60-ampere generator.
FRAME 1
1.
Hook up test lead (1) from generator B+ terminal (2) to G+ terminal (3) of
generator binding post on test stand.
2.
Hook up test lead (4) from generator ground (5) to G- terminal (6) of genera-
tor binding post on test stand.
3.
Hook up test lead (7) from generator ignition lead (8) to F terminal (9) of
generator binding post on test stand.
4.
Hook up test lead (10) between F-B terminal and IGN-SW terminal as shown.
END OF TASK