TM 5-2330-378-14&P
5-17. LOWERLINK ASSEMBLYREPLACEMENT(M870)(continued).
6
0
9
8
12
5
7
13.
Using two dolly jacks, support lower link assembly
(12) at each end.
5
14.
Screw slide hammer rod into nut (10). Usingslide
hammer, remove hinge pin (5) from semi-trailer
4
frame (3). Repeat for other hinge pin (5).
11
15.
Using two dollyjacks,
lowerand remove lowerlink
assembly (12) from gooseneck (6).
3
b.
INSTALLATION
1.
Place dolly jacks under front and rear ends of new lower link assembly (12). Slide lower link assembly (12)
into gooseneck (6) and raise into position.
2.
Drive two hinge pins (5) into lower link assembly (12).
If using old hinge pins, cut off nuts (10) and grind
weldment
smooth.
3.
Install two lubrication fittings (9) in two hinge pins (5).
4.
Remove two dolly jacks from lower link assembly (12).
5.
Using crane, raise gooseneck (6) to upright position.
6.
Install two lockpins (pare 2-8).
7.
Remove hydraulic jacks from under upper deck side rail (8).
8.
Behind semitrailer frame (3), install retaining ring (4) on hinge pin (5) and weld (refer to TC 9-237). Repeat
for other hinge pin (5).
9.
Using crane, lift gooseneck (6). Remove two wood blocks (1) from under two landing pads (2).
FOLLOW ON TASKS:
• Lower gooseneck (2-10).
• Unchock wheels (2-8).
5-45