INSTALLATION
1.
Connect ether cylinder relief tube (Figure 2, Item 4) to ether cylinder relief inlet adapter (Figure 2, Item 3).
2.
Connect atomizer ether supply tube (Figure 2, Item 7) to thermal close adapter (Figure 2, Item 9) and atomizer
(Figure 2, Item 8).
3.
Connect thermal close ether supply tube (Figure 2, Item 2) to thermal close adapter (Figure 2, Item 10) and
ether valve adapter (Figure 2, Item 5).
4.
Secure atomizer ether supply tube (Figure 2, Item 7) and thermal close ether supply tube (Figure 2, Item 2)
with three tiedown straps (Figure 2, Item 6).