INSTALLATION
- Continued
5.
Install heat control cable (Figure 4, Item 9) on control rod (Figure 4, Item 6) with spring nut (Figure 4, Item 7)
and cotter pin (Figure 4, Item 8).
6.
Install heat control cable (Figure 4, Item 9) on diverter bracket (Figure 4, Item 4) with retaining clip
(Figure 4, Item 5), clamp (Figure 4, Item 10), and screw (Figure 4, Item 11).
7.
Install defrost control cable (Figure 4, Item 14) on control rod (Figure 4, Item 2) with spring nut
(Figure 4, Item 1) and cotter pin (Figure 4, Item 13).
8.
Install defrost control cable (Figure 4, Item 14) on diverter bracket (Figure 4, Item 3) with retaining clip
(Figure
4, Item 1), clamp (Figure 4, Item 16), and screw (Figure 4, Item 12).
M5173DAA
6
5
4
3
2
7
8
9
11
10
12
13
14
15
16
1
Figure 4.
Defrost and Heat Controls Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
Check defrost and heat controls for proper operation. (TM 9-2320-272-10)
END OF TASK
END OF WORK PACKAGE
TM 9-2320-272-23-4
0745
0745-5/6 blank