REMOVAL
NOTE
All support rollers are removed basically the same way. This procedure is for left-rear
support
rollers.
1.
Remove seven screws (Figure 1, Item 2), clamps (Figure 1, Item 3), and cover (Figure 1, Item 4) from
underframe (Figure 1, Item 1).
2.
Remove two cotter pins (Figure 1, Item 5), support roller shaft (Figure 1, Item 7), and support roller
(Figure
1,
Item
6) from underframe (Figure 1, Item 1). Discard cotter pins.
M4011DAA
1
5
7
6
5
1
4
3
2
Figure 1.
Retractable Beam Assembly Removal.