TM 9-2320-361-34
I
10-4. DIFFERENTIAL CARRIER REPAIR
(Contd)
65. Install new safety wire
(11)
on two screws (10).
66. Install bearing cover (8) and shims (9) on carrier (12) with six new lockwashers (6) and screws (7).
Tighten screws (7) 65-85 lb-ft (88-115 N.m).
67. Remove flange (4) from pinion end
of
shaft (13).
68. Perform
step
69
if
dirt deflectors (5) were removed.
69. Install
two
dirt
deflectors
(5) on two flanges (4).
NOTE
✎
Apply
light
coat
of
GM grease to splines of flanges before
installation.
●
Flanges
must be installed with four holes alined.
●
Before tightening nuts, secure flanges in vise.
●
Ensure
cotter pin holes are alined before removing carrier
from vise.
70. Install spacer (14) and two flanges (4) on carrier
(12)
with two washers (3) and nuts (1). Tighten
nuts (1) 300-600 lb-ft (407-814 N.m).
71. Install two new cotter pins (2) in two nuts (1).
10-28