TM 9-2320-361-34
15-51. PIPELINE CONSTRUCTION
BODY MAINTENANCE (Contd)
I
b.
Flooring Removal
NOTE
Mark location of floorboards for proper installation.
1. Remove fourteen screws (2), washers (3), locknuts (10), two slats (4), and board (1) from
subframe (9). Discard locknuts (10).
2. Remove twenty-one screws (2), washers (3), locknuts (10), three slats (11), (6), and (4), two
boards (5), board (7), and board (8) from subframe (9). Discard locknuts (10).
3. Remove twenty-one screws (2), washers (3), locknuts (10), four slats (4), and three boards (5) from
subframe (9). Discard locknuts (10).
c. Inspection
1. Inspect boards (1), (5), (7), and (8) for warpage, rot, and splits that exceed board width. Replace if
warped, rotted, or splits exceed board width. Inspect two boards (1) for 1.31 in. (3.33 cm) thickness.
Replace if thickness is not correct.
2. Paint parts as needed (TB 43-0209).
I
e. Flooring Installation
1. Position two boards (1), boards (7) and (8), and five boards (5) on subframe (9) and install with seven
slats (4), forty-nine screws (2), washers (3), and new locknuts (10).
2.
Install two slats (11) and (6) on boards (7) and (5) and subframe (9) with seven screws (2),
washers (3), and new locknuts (10).
15-220