TM-9-2330-326-14-P

SEMITRAILER, TACTICAL, DROP DECK BREAKBULK/CONTAINER TRANSPORTER, 22-1/2 TON, M871A3

TECHNICAL MANUAL; OPERATOR’S, UNIT, DIRECT SUPPORT, AND GENERAL SUPPORT MAINTENANCE MANUAL (INCLUDING REPAIR PARTS AND SPECIAL TOOLS LIST)

FEBRUARY 2006

  TM-9-2330-326-14-P - Page 161 of 540

TM 9-2330-326-14&P
6-85
6-30. MANIFEST BOX REPLACEMENT.
This Task Covers:
a. Removal
b. Installation
c. Follow-On Tasks
Initial Setup:
Tools and Special Tools:
Tool kit, general mechanic’s (Item 4, Appendix B-3)
Equipment Conditions:
Landing legs down
Semitrailer disconnected from prime mover
Tires chocked
Ground boards emplaced
General Procedure:
a. Removal.
Remove four locknuts (3), washers (2), bolts (4), and document box (1) from semitrailer. Discard
locknuts.
b. Installation.
Install document box (1), four bolts (4), washers (2), and new locknuts (3).


Back to Top