TM 9--2350--311--10
Change 6
2--187
2--12 PREPARATION FOR FIRING — CONTINUED
2--12.2
Boresighting — Continued
f.
Comparison Test of the M140/M140A1 Alinement Device — Continued
2
Install a second M140/M140A1 alinement device (27). If using ERLS version, depress button (36.1) to
activate. Without moving position of M117/M117A2 panoramic telescope (18), view through eyepiece
(37). If M117/M117A2 panoramic telescope reticle and M140/M140A1 alinement device reticle aline, you
have verified accuracy of M140/M140A1 alinement device.
3
If M117/M117A2 panoramic telescope (18) reticle and second M140/M140A1 alinement device (27)
reticle do not aline, or if azimuth counter (19) reading is not correct after reticles are alined, one of two
M140/M140A1 alinement devices is unserviceable.