FRONT SIDE ARMOR ASSEMBLY REPLACEMENT - CONTINUED
0031 00
0031 00-5/(0031 00-6 Blank)
INSTALLATION - CONTINUED
WARNING
Use extreme caution when handling heavy parts. Provide adequate support and use assistance during proce-
dure. Failure to follow this warning may cause injury to personnel.
NOTE
Side armor assembly weighs 49 lb (22 kg).
2.
With assistance, position side armor assembly (5) and install four washers (2) and bolts (1) on side of cab.
3.
Connect side marker electrical connector (4) to cab wire harness.
4.
Install nine bolts (3) on side armor assembly (5).
5.
Install door assembly (WP 0015 00).
6.
Operate door and side marker to verify correct operation.
END OF WORK PACKAGE