1. INC-EPUU CABLE – A3279383-3 – QTY. 1
4. EPLRS POWER CABLE – A3004939 – QTY. 1
Figure 5-110.
Section XXXIX. EPLRS CABLES AND NTDR ANTENNA CABLE INSTALLATION
NOTE
• Loosen tunnel insulation before performing steps 39-1 and 39-2.
(Refer to TM 9-2320-280-20.)
• SINCGARS model AN/VRC-92F shown.
39-1.
Route INC-EPUU cable (1) from integrated rack (3), down through center access hole (2), and under
left-side tunnel insulation (5) towards rear of vehicle.
39-2.
Route power cable (4) from rear battery box forward and under integrated rack (3) and under
left-side tunnel insulation (5) towards rear of vehicle.
39-3.
Secure left-side tunnel insulation (5). (Refer to TM 9-2320-280-20.)
1
2
3
4
5
~
~
TUNNEL
INSULATION