TB 9-2320-302-13&P-2
UNDERBODY MINE BLAST PANEL REPLACEMENT - CONTINUED
0017 00
0017 00-15
INSTALLATION - CONTINUED
9.
Place two 6 ft long 2 in. x 4 in. supports across truck frame (11), under cab.
WARNING
Use extreme caution when handling heavy parts. Provide adequate support and use assistance during proce-
dure. Failure to follow this warning may cause injury or death to personnel.
10.
With assistance, install center underbody mine blast panel (9), eight washers (8), new lockwashers (7), and nuts (6).
11.
Remove two 6 ft long 2 in. x 4 in. supports.
12.
Push shift cable (10) through center underbody mine blast panel (9) and through hole to inside of cab.
440-016
6,7,8
9
10
11