TB 9-3950-253-13&P
Change 1
0007-32
0007
STOW LIFT FRAME – CONTINUED
NOTE
If required, place toggle switch in MAN position to complete stowing procedure.
15. Press and hold UP button (Figure 45, Item 2). As soon as hook arm is clear from bail bar, release button.
16. Press and hold STOW button (Figure 45, Item 1). When stowage guide reaches home position, release button.
17. Press and hold DOWN button until hook arm reaches home position, then release button.
NOTE
Lift frame is now held at top by stowage latch, at bottom by locking pins, and by hooks at
forward end of stowage guide rails.
Figure 45.
Stowed Lift Frame.
07
18. Set toggle switch (Figure 46, Item 1) to OFF.
Figure 46.
Toggle Switch at OFF.
07
END OF TASK
END OF WORK PACKAGE