TM 5--2350--378--24&P
0016 00--69
HYDRAULIC OIL OVERHEATS -- Continued
0016 00
Figure 50. Main Hydraulic Accumulator
MAIN HYDRAULIC ACCUMULATOR PRESSURE TEST -- CONTINUED
Tighten nut (Figure 50, item 7) on charge valve (Figure 50, item 6). Close nitrogen tank valve
(Figure 50, item 1). Back off regulator valve (Figure 50, item 2), open bleed valve (Figure 50,
item 10), and bleed hose pressure to 0 psi. Remove adapter valve (Figure 50, item 5) from
charge valve (Figure 50, item 6). Remove pressure measuring device (Figure 50, item 4) from
bleed valve (Figure 50, item 10) on charging harness (Figure 50, item 12). Install charge valve
cap (Figure 50, item 8) on charge valve (Figure 50, item 6). Install valve guard (Figure 50,
item 11).