TM-9-2320-272-23-3

TRUCK, 5-TON, 6X6, M939, M939A1, AND M939A2 SERIES TRUCKS (DIESEL)

TECHNICAL MANUAL; FIELD MAINTENANCE MANUAL; VOLUME 3 OF 5

SEPTEMBER 2012

  TM-9-2320-272-23-3 - Page 768 of 1469

INSTALLATION
NOTE
Wrap all male pipe threads with antiseize tape before installation.
1.
Install check valve (Figure 2, Item 3) on tee (Figure 2, Item 4).
2.
Install check valve adapter (Figure 2, Item 2) on check valve (Figure 2, Item 3).
3.
Connect air line (Figure 2, Item 1) to check valve adapter (Figure 2, Item 2).
1
2
3
4
M9489DAA
Figure 2.
Air Reservoir One-Way Check Valve Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
Start engine and allow air pressure to build up to normal operating range. Check for air leaks at check valve.
Road test vehicle. (TM 9-2320-272-10)
END OF TASK
END OF WORK PACKAGE
TM 9-2320-272-23-3
0437
0437-3/4 blank


Back to Top