TM-9-2320-272-23-4

TRUCK, 5-TON, 6X6, M939, M939A1, AND M939A2 SERIES TRUCKS (DIESEL)

TECHNICAL MANUAL; FIELD MAINTENANCE MANUAL; VOLUME 4 OF 5

SEPTEMBER 2012

  TM-9-2320-272-23-4 - Page 730 of 1393

INSTALLATION - Continued
M5237DAA
4
1
2
3
Figure 4.
Front Winch Cable Clevis Installation.
5.
Wrap upper ends of strands (Figure 5, Item 2) with mechanic's wire (Figure 5, Item 3).
NOTE
Approximately 1-3/8 in. (3.5 cm) of cable should extend above threaded sleeve.
6.
Slide threaded sleeve (Figure 5, Item 1) over end of cable (Figure 5, Item 5) and seat against mechanic's wire
(Figure 5, Item 4).
7.
Remove cable (Figure 5, Item 5) from vise and reclamp on the hex-flats of threaded sleeve (Figure 5, Item 1).
8.
Remove upper wire (Figure 5, Item 3) from cable (Figure 5, Item 5).
M5238DAA
1
2
3
4
5
Figure 5.
Front Winch Cable Clevis Installation.
TM 9-2320-272-23-4
0675
0675-5


Back to Top