INSTALLATION - Continued
8.
Install conduit (Figure 4, Item 2) on dump body frame (Figure 4, Item 8) and cab protector (Figure 4, Item 12)
with ten clamps (Figure 4, Item 6), screws (Figure 4, Item 5), and locknuts (Figure 4, Item 7).
9.
Install conduit (Figure 4, Item 2) on cab protector (Figure 4, Item 12) with eighteen clamps (Figure 4, Item 11),
screws (Figure 4, Item 10), and locknuts (Figure 4, Item 1).
10.
Connect four cable leads (Figure 4, Item 4) to two convoy warning lights (Figure 4, Item 3).
3
4
5
M9551DAA
1
2
3
4
2
6
7
8
9
10
11
12
Figure 4.
Convoy Warning Light Harness Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
Lower dump bed. (TM 9-2320-272-10)
END OF TASK
END OF WORK PACKAGE
TM 9-2320-272-23-5
0797