2-46.
STEKE-R
TEST PROCEDURES
(Cont’d)
STARTER SOLENOID VOLTS TEST #70
Description:
This procedure
measures the voltage present
at the starter solenoids positive terminal. Test
requires DCA hookup only.
Typical Applications:
Control Functions:
Check starter solenoid volts.
01,02,
03, 04,06
Test Procedure:
1. Disconnect fuel solenoid wire 54A to prevent
starting.
2. Set TEST SELECT switch to 70.
3. Press and release TEST button.
4. Crank the engine and observe the displayed
voltage.
Pre-Test Procedures:
Run confidence
test.
Possible Error Messages:
None.