DECK
This task covers:
Repair (page 5-91)
INITIAL SETUP
Tools
Bar, pry
Drill bit, 11/32-inch
Drill bit, 5/8-inch
Drill, electric, portable, 1/2-inch
Hammer, ball-peen, machinist’s, 2-lb
Handle, ratchet, 1/2-inch drive
Saw, hand, crosscut
Screwdriver, cross-tip, number two
Screwdriver, flat-tip, 3/16-inch
Socket, 1/2-inch drive, 1/2-inch
Personnel Required
Two
ACTION
LOCATION
ITEM
REMARKS
REPAIR
NOT E
The deck is made up of eighteen long boards laid side by side and eighteen short boards
side by side. This is a typical procedure for replacement of one board.
The boards are fitted together with tongue and groove. To replace a board other than
the two outer boards, you must remove each board between the damaged board(s) and
the closest wall, working from the outside in.