TM 9-2330-335-14&P
0051-2
0051
INSTALLATION
00051
1.
Install ground board (Figure 2, Item 6) onto semitrailer and install clip (Figure 2, Item 4) and chain link (Figure
2, Item 5).
2.
Install two new cotter pins (Figure 2, Item 1), washers (Figure 2, Item 2), and one pin (Figure 2, Item 3) on
semitrailer bracket.
Figure 2.
Ground Boards.
051
END OF TASK
FOLLOW-ON TASKS
00051
1.
Secure ground board (Figure 2, Item 6) using clip (Figure 2, Item 4) to take up slack in chain. Pull on handle to
ensure ground board will not slide out during operation.
2.
Connect semitrailer to prime mover.
3.
Remove tire chocks.
4.
Raise landing legs.
END OF TASK
END OF WORK PACKAGE