INSTALLATION - Continued
6.
Install safety lock pin (Figure 9, Item 3) on ISO lock mount (Figure 9, Item 1).
NOTE
Install shims as noted prior to removal.
7.
With the aid of an assistant, install ISO lock mount (Figure 10, Item 4), two shims (Figure 10, Item 3), and shim
(Figure 10, Item 5) on trailer (Figure 10, Item 1) with two washers (Figure 10, Item 6), screws (Figure 10, Item
7), and locknuts (Figure 10, Item 2). Tighten screws to 680 lb-ft (922 N·m).
2
3
4
5
6
7
1
Figure 10.
ISO Lock Mount Installation.
8.
Install marker light bracket (Figure 11, Item 10) and cushion clip (Figure 11, Item 2) on ISO lock mount (Figure
11, Item 1) with four washers (Figure 11, Item 3), lockwashers (Figure 11, Item 4), and screws (Figure 11, Item
5).