RIGGING THE BOOM
NOTE
•
Auxiliary hydraulic system is used in an emergency to raise or lower boom under
no-load condition.
•
Two snatch blocks are provided for hoisting operations, one 10-ton (9.1-metric ton)
and one 25-ton (22.7-metric ton).
END OF TASK
RIGGING 10-TON SNATCH BLOCK
CAUTION
In order not to tangle cable when rigging, read following instructions carefully. Failure to
comply may result in damage to equipment.
1.
Place 10-ton (9.1-metric ton) snatch block (Figure 1, Item 1) in boom tray (Figure 1, Item 5) with open end of
snatch block facing forward.
2.
Swing hook (Figure 1, Item 4) out and lift hinge (Figure 1, Item 3).
3.
Open boom pulley safety latch (Figure 1, Item 2).
Figure 1.
10-Ton Snatch Block.
TM 9-2350-256-10
0076
0076-2