RIGGING 25-TON SNATCH BLOCK - Continued
4.
Have operator payout hoist cable (WP 0079). Pass hoist cable (Figure 4, Item 3) over top of crew
compartment and under boom crossmembers (Figure 4, Item 2). Keep hoist cables between staylines
(Figure 4, Item 1).
5.
Pass hoist cable (Figure 4, Item 3) up and over left side of boom travel lock support (Figure 4, Item 4).
6.
Bring hoist cable (Figure 4, Item 3) back, going up and over left boom pulley (Figure 4, Item 6).
7.
Pull hoist cable (Figure 4, Item 3) forward and lay it on the lower pulley (Figure 4, Item 7) of
25-ton (22.7-metric ton) snatch block (Figure 4, Item 5) from left to right.
Figure 4.
Rigging 25-Ton Snatch Block.
8.
Bring cable (Figure 5, Item 1) back over upper boom crossmember (Figure 5, Item 4) and down under boom
pulley assembly (Figure 5, Item 5).
9.
Pull cable (Figure 5, Item 1) up and over right boom pulley (Figure 5, Item 3).
10.
Close boom pulley safety latch (Figure 5, Item 2).
Figure 5.
Boom Pulley Safety Latch.
TM 9-2350-256-10
0076
0076-5