TM-9-2350-260-20-1-2

TANK, COMBAT, FULL TRACKED 105-MM GUN, M60 2350-00-678-5773 (HULL)

TECHNICAL MANUAL; ORGANIZATIONAL MAINTENANCE VOLUME 2 OF 4, CHAPTERS 5 THRU 9

  TM-9-2350-260-20-1-2 - Page 132 of 772

TM 9-2350-260-20-1-2
CYLINDER HEAD AND OIL PAN DRAIN TUBES (LEFT AND RIGHT) REPLACEMENT (Sheet 4 of 4
8.
Position two bolts and new lockwashers (G) through lower drain tube end and place new gasket (H) over bolts.
9.
Using 1/2 inch socket, tighten two bolts and lockwashers (G) to engine.
10.
Using screwdriver, tighten 16 clamps (B) on hoses on each end of lower drain lines assembly.
11.
Holding nut with 3/8 inch wrench and using screwdriver, connect four fuel line clamps (J) to oil drain line.
12.
Install powerplant left bank oil cooler frame and brackets (2D engine, page 6112) as required).
13.
Install powerplant right bank oil cooler frame and brackets (2D engine, page 6102) (as required).
14.
Install powerplant (2A engine) oil coolers frame and brackets (page 6-95).
15.
Replenish engine off (LO 9-2350-260-12).
16.
Connect powerplant test equipment (ground hop kit) (Item 32, Chapter 3, Section I) (page 5-54).
17.
Start engine and check for leaks.
18.
Disconnect powerplant test equipment (ground hop kit) (page 5-67).
19.
Install 2A powerplant (page 5-14) or 2D powerplant (page 540).
End of Task
TA147509
6-55


Back to Top