TM-9-2350-261-20-2

CARRIER, M113A2, M577A2, M1064, M1068, M1059 AND M901A1

TECHNICAL MANUAL; UNIT MAINTENANCE MANUAL - VOLUME 2 OF 4

  TM-9-2350-261-20-2 - Page 284 of 1008

TM 9-2350-261-20-2
REPLACE DISTRIBUTION BOX ASSEMBLY FOR 100 AMP GENERATOR
SYSTEM (M901A1 ONLY) — Continued
0268 00
2.
Install new grommet (5) and circuit 400 lead (6) in distribution box (3).
NOTE
If bilge pump circuit breakers were removed, see WP 0327 00 for installation. If bilge pump
circuit breakers were not removed, go to Step 6.
3.
Connect circuit 450C lead (7) to circuit breaker (8).
4.
Connect circuit 450A lead (9) to circuit breaker (10).
5.
Install circuit 450C lead (7) on bus bar (11). Secure with new lockwasher (12) and screw (13).
6.
Install grommet (14) and circuit 450 lead (15) in distribution box (3). Connect circuit 450 lead to circuit breaker (16).
7.
Install new grommet (17) and circuit 450B lead (18) in distribution box (3). Connect circuit 450B lead to circuit
breaker (19).
8.
Install new grommet (20) and circuit 2 lead (21) in distribution box (3).
9.
Install new grommet (22) and circuit 3 lead (23) in distribution box (3). Install circuit 3 lead on circuit breaker (24).
Secure with new lockwasher (25) and screw (26).
0268 00-4


Back to Top