TM 9-2350-261-20-2
REPLACE DISTRIBUTION BOX ASSEMBLY FOR 100 AMP GENERATOR
SYSTEM (M577A2 ONLY) — Continued
0267 00
2.
Install new grommet (5) and circuit 2A lead (6) in distribution box (3).
3.
Install new grommet (7) and circuit 2 lead (8) in distribution box (3).
NOTE
If bilge pump circuit breakers were removed, see WP 0327 00 for installation. If bilge pump
circuit breakers were not removed, go to Step 7.
4.
Connect circuit 450C lead (9) to circuit breaker (10).
5.
Install circuit 450C lead (9) on bus bar (11). Secure with new lockwasher (12) and screw (13).
6.
Connect circuit 450A lead (14) to circuit breaker (15).
7.
Install new grommet (16) and circuit 450B lead (17) in distribution box (3). Connect circuit 450B lead to circuit
breaker (18).
8.
Install new grommet (19) and circuit 450 lead (20) in distribution box (3). Connect circuit 450 lead to circuit breaker
(21).
9.
Install new grommet (22) and circuit 3 lead (23) in distribution box (3). Install circuit 3 lead on circuit breaker (24).
Secure with new lockwasher (25) and screw (26).
10. Install wiring harness (27) on bus bar (11). Secure with new lockwasher (28) and screw (29).
0267 00-4