TM 9-2350-261-20-2
REPLACE AUXILIARY TANK DEAERATION HOSES — Continued
0209 00
3.
Remove two hoses from carrier.
INSTALLATION
1.
Secure two hoses (2) to elbows (3) with clamps (1).
2.
Secure two hoses (2) to elbows (5) and (7) with clamps (4) and (6).
FOLLOW-THROUGH STEPS
WARNING
Wearing loose clothing around moving parts can allow personnel to get caught and cause injury
or death. Tuck in loose clothing.
1.
Fill cooling system (WP 0194 00).
2.
Start engine (see your -10). Check for leaks.
3.
Stop/shutdown engine (see your -10).
4.
Close power plant front access door and raise trim vane (see your -10).
END OF TASK
0209 00-2