19. Install cover (1) on connector (2).
20. Install wiring harness (7).
21. Install washer insulator (3), washer (4), new lockwasher (5), and new locknut (6) on wiring harness (7).
22. Install rubber bushing (8), end seal plug (9), packing retainer (10), spring washer (11), and coupling nut (12) on wiring
harness (7).
23. Feed wiring harness (7) through bushing (13) and secure with washer (14), new lockwasher (15), and new locknut (16).
24. Install connectors (17) and (18) on wiring harness.
25. Connect circuit 7 lead (17) and circuit 799 lead (18) inside carrier.
26. Repeat Steps 19 - 25 for opposite side of carrier.
FOLLOW-THROUGH STEPS
1.
Install base and plate (WP 0576 00).
2.
Close power plant front access door and raise trim vane (see your -10).
3.
Connect battery ground lead (WP 0294 00).
END OF TASK