b. Installation
1
2
3
4
5
Install ground lead (4), two new Iockwashers (14), and screw (13) to bulkhead.
Install insulator (12), new gasket (11 ), and slave start receptacle assembly (10).
Install protective cover (9) on receptacle assembly (10).
Install four flat washers (7), four new Iockwashers (6), four screws (8), and four nuts (5). Ensure protective
cover (9) cord is attached under one screw.
Connect ground lead (4) and power lead (3), two new Iockwashers (2), and two screws (1). Wrap exposed wire
connections with tape.
NOTE
FOLLOW-ON MAINTENANCE:
Connect
batteries (para 8-10)
8-39 EXTERNAL POWER RECEPTACLE (M109A4/M109A5)
This task covers:
a. Removal
b. Installation
INITIAL SETUP
Applicable Configurations
Gasket (item 162, Appx G)
M109A4/M109A5
Lockwasher (item 54, Appx G)
Lockwasher (item 80, Appx G)
T
OO
I
S
Lockwasher (item 111, Appx G)
General mechanic’s tool kit (item 64, Appx H)
Lockwashers (4) (item 87, Appx G)
Materials/Parts
Equipment Condltlons
. .
Electrical tape — black (item 62, Appx D)
Batteries disconnected (para 8-28)
8-96