STOWAGE ASSEMBLY PLACEMENT – CONTINUED
PLS Stowage Assembly Bolt Tightening
00021
7. Tighten 12 bolts (Figure 24, Item 1) and nuts (Figure 24, Item 2) securing stowage assembly to support
brackets (Figure 24, Item 5).
8. Tighten 14 bolts (Figure 24, Item 3) and nuts (Figure 24, Item 4) securing support brackets (Figure 24, Item 5)
to frame.
Figure 24.
Tighten PLS Bolts.
0021
END OF TASK
FOLLOW-ON TASKS
00021
1. Install toolbox - HEMTT only (TM 9-2320-326-14&P).
2. Stow lift frame on vehicle (WP 0007).
END OF TASK
END OF WORK PACKAGE