TM-5-3805-254-14-P-2

TRUCK, DUMP, 20 TON, 6X4, ON-OFF HIGHWAY 71,000 GVW, IHC MODEL F-5070 (CCE)

TECHNICAL MANUAL; OPERATOR’S, ORGANIZATIONAL, DIRECT SUPPORT, GENERAL SUPPORT AND DEPT MAINTENANCE MANUAL (INCLUDING REPAIR PARTS INFORMATION AND SUPPLEMENTAL MAINTENANCE INSTRUCTIONS)

JUNE 1980

  TM-5-3805-254-14-P-2 - Page 761 of 894

TRUCK SERVICE MANUAL
TRANSMISSION
INSPECTION AND REBUILD
Para 6-17/ 6-18
to the forward-clutch housing. Install the PTO gear,
chamfered end of internal splines first, from the rear of
the clutch housing.
Slide the gear onto the housing until
the snapring engages its mating groove in the gear.
(21)
Grease and install two hook-type sealrings
4 (A, foldout 11). Install hook-type sealring 1 on the front
of the turbine shaft.
Install thrust bearing race
2, cupped
side first, onto the front of the forward clutch housing.
(22)
Grease (with oil-soluble grease) and install
bearing race 25, flat side first, and needle bearing 26
onto the rear of forward clutch hub 20.
6-18. FOURTH CLUTCH ASSEMBLY
a. Disassembly (B, foldout 11)
(1) Remove the bearing race from the front hub
of the fourth-clutch housing (fig. 6-38).
(2) Remove the bearing race from the rear
hub
of the fourth-clutch housing (fig. 6-39).
(3) Place the fourth-clutch assembly, snapring
up, on the work table.
(4) Remove the large snapring and the back
plate
(fig.
6-40).


Back to Top