ARMY TM 9-1290-365-24&P
CHAPTER 4
UNPACKING AND INSTALLATION
CHAPTER CONTENTS
Subject
Page
General.
........................................................................................................................................
4-1
Unpacking.
....................................................................................................................................
4-1
Installation.
....................................................................................................................................
4-1
Installation of Transceiver Assy on Gun .
.....................................................................................
4-2
System Interconnection.
...............................................................................................................
4-2
4.1 GENERAL.
This chapter describes procedures required for proper unpacking and installation of the M93 MVS.
4.2 UNPACKING.
a. Open packaging and verify that all parts are present. Refer to Table 1-1 and Figure 1-1.
b. Inspect Transceiver Assy and verify:
(1) No external mechanical damage to Transceiver housing.
(2) No connector pins are bent or broken.
(3) Transceiver Assy is properly fastened to Mounting Bracket Assy. If necessary, tighten
four screws using 5-mm hex key wrench.
c. Inspect cables and verify:
(1) No external mechanical damage.
(2) No connector pins are bent or broken.
NOTE
Remember to place dust caps on connectors when not in use.
4.3 INSTALLATION.
Refer to Figure 4-1. Installation of the system units is performed in the following steps:
a. Install Transceiver Assy with connected Mounting Bracket Assy on non-recoiling part of
gun.
b. System interconnection.
4-1