TM 9-2320-209-20-3-1
7-19.
FRONT SERVICE HEADLIGHT ASSEMBLY ADJUSTMENT.
TOOLS:
Flat-tip screwdriver
50-foot tape measure
Carpenter’s square
SUPPLIES:
Chalk, SS-C-266F
String
PERSONNEL: Three
EQUIPMENT CONDITION:
Truck parked, engine off, handbrake set.
1.
Using tape measure and chalk, draw line (1) 25 feet from and parallel to
vertical wall (2).
2.
Start unloaded truck. Refer to TM 9-2320-209-10. Move truck so that head
lights (3) are parallel with and directly above line (1). The center line of
truck (4) will be at right angle (90°) to wall (2) as shown.
3.
Stop engine and set handbrake. Refer to TM 9-2320-209-10.