INSTALLATION - Continued
NOTE
Step (14) applies only to vehicles equipped with a front winch with level wind.
14.
Install winch level wind (Figure 20, Item 2) on winch (Figure 20, Item 5) with four lockwashers
(Figure
20,
Item
4) and screws (Figure 20, Item 3). Tighten screws 70 to 90 lb-ft (95 to 122 N·m).
15.
Connect two wires (Figure 20, Item 7) to neutral start switch (Figure 20, Item 8) on transmission
(Figure
21,
Item 6).
16.
Connect wires (Figure 20, Items 10 and 11) to 5th gear lock-in connector (Figure 20, Item 9).