FRONT WHEEL INSTALLATION
1.
Install two front wheels (Figure 6, Item 2) on wheel hub studs (Figure 6, Item 1) with 20 wheel stud nuts
(Figure
6,
Item
3). Hand-tighten stud nuts.
2.
Raise front of vehicle clear of jack stands, remove jack stands, and lower vehicle.
3.
Tighten 20 wheel stud nuts (Figure 6, Item 3) 325 to 355 lb-ft (441 to 481 N·m) in sequence shown.
3
2
1
M5006DAA
1
2
3
4
5
6
7
8
9
10
Figure 6.
Wheel and Tire Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
Spare tire installed. (TM 9-2320-272-10)
END OF TASK