5.
Position crosshead (Figure 6, Item 9) on piston rods (Figure 6, Item 7) and install with two upper crosshead
retainers (Figure 6, Item 6), lower crosshead retainers (Figure 6, Item 8), four lockwashers
(Figure
6,
Item
1), and screws (Figure 6, Item 2).
6.
Raise hoist cylinders (Figure 6, Items 4 and 10) and remove wood block (Figure 6, Item 3).
M10231DAA
1
2
3
4
5
6
7
8
9
10
Figure 6.
Dump Hoist Cylinder Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Install dump roller arms. (WP
0723)
2.
Install dump body. (WP
0594)
3.
Fill hydraulic reservoir to proper oil level. (Volume 5, WP
0820)
4.
Start engine and operate dump through full range. Check for leaks and proper operation. (TM 9-2320-272-10)
END OF TASK
END OF WORK PACKAGE