INSTALLATION
1.
Position frame rail sill (Figure 4, Item 4) on cargo body (Figure 4, Item 5).
2.
Install frame rail sill (Figure 4, Item 4) on cargo body (Figure 4, Item 5) with ten screws (Figure 4, Item 3),
lockwashers (Figure 4, Item 2), and nuts (Figure 4, Item 1), ensuring heads of screws rest in sill of counterbore.
Tighten nuts 100 to 110 lb-ft. (11 to 12 N·m).
2
M3009DAA
1
5
4
3
Figure 4.
Frame Rail Sill Installation.
END OF TASK
FOLLOW-ON MAINTENANCE
Install cargo body assembly. (WP
0588)
END OF TASK
END OF WORK PACKAGE