INSTALLATION
1.
Install grommet (Figure 2, Item 3) on junction box (Figure 2, Item 4).
2.
Install telephone jack post (Figure 2, Item 5) on grommet (Figure 2, Item 3) and junction box
(Figure
2,
Item
4) with nut (Figure 2, Item 8).
3.
Install two leads (Figure 2, Item 2) on telephone jack post (Figure 2, Item 5) with screw (Figure 2, Item 1).
4.
Install junction box (Figure 2, Item 4) on panel (Figure 2, Item 7) with four screws (Figure 2, Item 6).
3
4
5
M9921DAA
1
2
8
6
7
A
B
Figure 2.
Inside Telephone Jack Post Installation.
END OF TASK
END OF WORK PACKAGE